Postby PinkyF » Tue Jan 19, 2016 10:55 pm

Hello and thank you for your interest in large wood and King County rivers!
The Tolt Pipeline Protection Project is at 60 percent design and an Instream Project Design Checklist has been completed. As part of the project, large wood will be placed in the Snoqualmie River. Both the plans and checklist are posted on the project web page and the King County Large Wood Project Installation web page (links below).
At earlier design phases, the Tolt Pipeline Protection Project (formerly known as the Winkelman Revetment Project) was presented at both the 2014 and 2015 Large Wood Annual Meeting, hosted by King County (presentation links below).
The Tolt Pipeline Protection Project is located on the right (north) bank of the Snoqualmie River at River Mile 12.9-13.1, south of Duvall. The primary project goal is to reconstruct the revetment on the north side of the river that protects the Tolt River water supply pipeline.
Final project design will be completed in the first quarter of 2016 and construction is scheduled for summer and fall of 2016. If you have questions or comments, please contact Chase Barton, Senior Engineer, River and Floodplain Management Section at 206-477-4854 or chase.barton@kingcounty.gov.
Project information:
• Tolt Pipeline Protection Project
• Instream Project Design Checklist for Tolt Pipeline Protection Project (PDF, 573KB)
• 60% Design Plans for the Tolt Pipeline Protection Project (PDF, 37MB)
• Large wood installation projects in King County
• 2014 Large Wood Annual Meeting Presentation (PDF, 14MB)
• 2015 Large Wood Annual Meeting Presentation (PDF, 5MB)

________________________________________
PinkyF
 
Posts: 263
Joined: Wed Apr 16, 2014 5:07 pm

Return to General Discussion

Who is online

Users browsing this forum: No registered users and 1 guest

cron